TN: Kudankulam Nuclear Power Plant commissioning postponed Chennai: Nuclear Power Corporation of India Ltd has postponed the expected date of commissioning of the first unit of Kudankulam Nuclear Power Plant to June. With a physical progress completed upto 99.66 per cent, the 1,000 MW first unit is expected to be commissioned in June, NPCIL website said.

Earlier, NPCIL expected it to be commissioned by May. NPCIL is building two 1,000 MW VVER nuclear power units with Russian collaboration at Kudankulam in Tirunelveli district of Tamil Nadu.

The Supreme Court had on May 6 cleared hurdles in commissioning of the controversial plant, saying that the safety and security requirements have been taken care of and the project would benefit larger public interest. The project has missed several deadlines since December 2012 following protests by locals over safety concerns.

...more    
01:26 AM, May 15, 2013

Commissioning of Kudankulam N-plant likely to get delayed
by IANS
Chennai: India's atomic power plant operator, Nuclear Power Corporation of India Ltd (NPCIL) has shifted the commissioning of the first 1,000 MW unit at the Kudankulam Nuclear Power Project (KNPP) to June 2013. According to NPCIL's website, the first unit, whose physical progress is at 99.66 per cent, will be commissioned next month, not in May as earlier announced. Soon after the Supreme Court gave its nod to the project...  
10:57 PM, May 14, 2013

'Kudankulam plant is almost ready to begin functioning'
by IANS
Chennai: The first unit of the 1,000 MW Kudankulam Nuclear Power Plant (KNPP), set up by Nuclear Power Corporation of India Ltd. (NPCIL), is almost ready for beginning the fission process, said a top official of the country's atomic regulator. "As of now, the test reports and the results submitted by NPCIL relating to the first unit of KNPP are satisfactory. A team of experts will be going to KNPP...  
11:25 PM, May 07, 2013

Kudankulam Nuclear Plant decision now lies with the regulator
by IANS
Chennai: With the apex court giving its nod Monday for the first 1,000 MW unit of the Kudankulam Nuclear Power Project (KNPP), it is now for the regulatory board to give its sanction to operationalise it, an official said. The ball is now in the court of the Atomic Energy Regulatory Board (AERB) to give its sanction to operationalise the first unit of KNPP near Chennai, said the official of...  
03:56 PM, May 06, 2013

SC approves commissioning of Kudankulam Nuclear Power Plant New Delhi: The Supreme Court has given a go ahead to the commissioning of the Kudankulam Nuclear Power Plant. The court has observed that the plant has been set up for the welfare and sustainable growth of the people. The apex court verdict came on a plea seeking halt to the commissioning of the Kudankulam Nuclear Power Plant till the implementation of key additional safety measures suggested after an n-accident...  
11:00 AM, May 06, 2013

SC to decide the fate of Kudankulam nuclear power plant today New Delhi: Ahead of the Supreme Court verdict on the Kudankulam nuclear reactor, sources confirm that the reactor has been fully loaded and tests are presently underway. The reactor is expected to start functioning sometime in May, but full production of 1,000 megawatts will take between six to eight months as the power generation will be in phases beginning with 50 megawatts which will then be gradually scaled up. Meanwhile,...  
07:21 AM, May 06, 2013

SC to decide fate of Kudankulam n-project on Monday
by IANS
New Delhi: The Supreme Court on Monday is expected to pronounce its verdict on a plea seeking halt to the commissioning of the Kudankulam Nuclear Power Plant till the implementation of key additional safety measures suggested after an n-accident in Japan. The petitioner, Chennai-based IT professional G Sunderrajan, wants the government to implement 11 of the 17 additional safety measures recommended for the Kudankulam Nuclear Power Plant (KNPP) by a...  
11:15 PM, May 05, 2013

SC moved to seek halt to Kudankulam plant's commissioning New Delhi: The Supreme Court was moved on Tuesday, seeking a direction to the government not to take steps for commissioning the Kudankulam nuclear plant in Tamil Nadu till allegations of use of sub-standard equipment and the impact on the reactor and the public safety were probed. The application by G Sundarrajan has sought directions to the government not to bring the nuclear power plants reactors to initial criticality till...  
04:29 AM, Apr 24, 2013

'Sub-standard equipment used in Kudankulam plant' New Delhi: An anti-nuclear activist on Tuesday approached the Supreme Court seeking to restrain the Centre from commissioning the Kudankulam nuclear plant alleging that sub-standard equipment have been used in the plant making it unsafe. The petitioner, on whose plea against the plant the apex court has reserved its verdict, filed an application alleging that new "revelation" has come to light which raises questions on the safety of the plant....  
07:45 PM, Apr 23, 2013

Commission Kudankulam plant after probe: Achuthanandan
by IANS
Thiruvananthapuram: Contending serious defects are now surfacing at the Kudankulam Nuclear Power Project (KNPP), CPI-M leader VS Achuthanandan on Sunday demanded theta it should be commissioned only after a probe to find out lapses in safety measures. In a statement issued here, the former Kerala chief minister and veteran Communist party of India-Marxist (CPI-M) leader said that the atomic regulator, Atomic Energy Regulatory Board's former chairman A Gopalakrishnan and a...  
04:38 AM, Apr 22, 2013

Defective valves found in Kudankulam pre-commissioning tests Mumbai: India's nuclear regulator ordered replacement of four defective valves of the system that cools the reactor of Kudankulam nuclear power plant after the problem was detected during ongoing pre-commissioning tests. The defect in the components of the four valves--there are thousands of such devices in a nuclear reactor--was found during pre-commissioning tests early this year, officials said. "During testing of thousands of valves installed in the plant, the performances...  
02:14 AM, Apr 20, 2013

Kudankulam to begin power production in April
by IANS
New Delhi: Power production by the first unit of the Kudankulam atomic plant will start in April 2013, Minister of State in the Prime Minister's Office V Narayanasamy said on Wednesday. He said that the second unit would start production by October 2013. Narayanasamy told reporters in New Delhi that Indian and Russian scientists had checked the parameters of the plant and the system was working well. "All parameters are...  
02:50 AM, Apr 04, 2013

Lack of fuel reason for power shortage: Electricity Authority Shortage of fuel - both gas and coal - was the only reason for the growing electricity scarcity in the country, particularly in the south, Central Electricity Authority Chairman AS Bakshi said in Hyderabad on Saturday. "Coal shortage will continue for at least 3-4 years though we have adequate reserves. Domestic coal supply to power generating stations has increased by eight per cent in 2013, but still there will be...  
02:30 AM, Mar 31, 2013

Kudankulam I will be operational in April: Manmohan Singh The controversial Kudankulam Unit I of the atomic power reactor in Tamil Nadu will become operational by April, Prime Minister Manmohan Singh has said. He gave this assurance to Russian President Vladimir Putin when the two met here on Tuesday night on the sidelines of the BRICS summit. ...  
12:41 PM, Mar 27, 2013

India irked by false Lankan media reports on Kudankulam India on Wednesday dismissed as "totally baseless" Sri Lankan media reports on alleged radiation leaks at Kudankulam nuclear power station in Tamil Nadu. ...  
02:26 AM, Mar 07, 2013

Full text: President Pranab Mukherjee's speech in Parliament The Budget Session of Parliament has formally begun with President Pranab Mukherjee's address in which he laid out the government's agenda in the forthcoming session. Pranab Mukherjee spoke on issues including safety of women, economic slowdown, inflation and also laid stress on cross-border relations. ...  
12:57 PM, Feb 21, 2013

'Kudankulam could be commissioned in few days' The first 1,000 MW unit of the much-delayed Kudankulam nuclear power project (KNPP) could be commissioned in the next few days and every step is being taken to ensure safety, a senior official said. ...  
09:29 PM, Feb 08, 2013

Commercial operation of Kudankulam plant delayed The commercial operation of the controversial Kudankulam Nuclear Power Project (KNPP) has been delayed further and is expected to commence in February. The commercial operation of the 1000 MW first unit of the Indo-Russian project, which had been delayed following anti-nuclear protests, was expected in February, the Nuclear Power Corporation Limited (NPCIL) said. ...  
01:21 PM, Jan 12, 2013

Kudankulam station director receives threat letter Even as the controversial Kudankulam Nuclear Power plant is set to be commissioned in January, an anonymous letter threatening its site director has sent the authorities and police into a tizzy. The letter, addressed to Director RS Sundar and received by post Friday evening, warned that Sundar would be eliminated if he went ahead with commissioning of the plant, police said. ...  
01:36 PM, Jan 05, 2013

Kudankulam unit-1 to be commissioned in 2 weeks: AEC The much-delayed Kudankulam project is set to be commissioned within the next two weeks as nuclear scientists have entered the final lap of a series of tests on its safety and efficacy. "Within this month 100 per cent. It will take about two weeks," Ratan Kumar Sinha, Chairman of the Atomic Energy Commission said here on the sidelines of the 100th Indian Science Congress when asked about the commissioning of...  
11:59 AM, Jan 03, 2013